Project progress--2020.5.16

On May 16, 2020, the first open day for owners of small courtyards in Dacheng after the establishment of the Interim Committee. Representatives of the Interim Committee and Tahoe staff entered the construction site to understand the progress after taking safety precautions. On rainy days, workers happened to be taking shelter from the rain, and almost no workers were seen at the construction site. Due to safety concerns, access to the center field was not allowed.

On May 16, 2020, the first open day for owners of small courtyards in Dacheng after the establishment of the Interim Committee. Representatives of the Interim Committee and Tahoe staff entered the construction site to understand the progress after taking safety precautions. On rainy days, workers happened to be taking shelter from the rain, and almost no workers were seen at the construction site. Due to security concerns, access to the center field is not allowed.

Due to viewing angle issues, only the main structure can be seen, and there may be a slight deviation in reality, especially in the south area, where the view is not clear near the south. At present, except for the model houses, the decoration of the north and south finely decorated houses has not yet started.

North area perspective: 7#14th floor

South area perspective: Floor 1#9

4.15 Announcement of progress▼

The North District has all been sold out. The following table shows the progress of the main unfinished houses in the North District.

North District 4.15 Announcement of progress 5.16 Construction site progress

1#

Construction of the main 7th floor completed

The 9th floor is under construction

4#

Construction of the main 7th floor completed

The 8th floor is under construction

11# Construction of main 3 floors completed The 3rd floor is under construction
12# Main 2nd floor construction completed The 2nd floor is under construction
13# Main 2nd floor construction completed The 2nd floor is under construction
14# Construction of the first floor of the main body is completed The 2nd floor is under construction
15# Main 2nd floor construction completed The 3rd floor is under construction
16# Main 2nd floor construction completed The 2nd floor is under construction
17# Construction of main 3 floors completed The 2nd floor is under construction
18# Main roof construction Uncapped
24# Main body capping, secondary structure construction Missing roof tiles
25# Main body capping, secondary structure construction Missing roof tiles
26# Main body capping, secondary structure construction Missing roof tiles
27# Main body 3 floors completed The 4th floor is under construction
28# Main body capping, secondary structure, floor construction Missing roof tiles
29# Main body capping, secondary structure, floor construction Missing roof tiles
30# Main body capping, secondary structure, floor construction Missing roof tiles
31# Main body capping, secondary structure, floor construction The roof of the floor is not done yet
32# Main body capping, secondary structure, floor construction The roof of the floor is not done yet
33# Main body capping, secondary structure, floor construction The roof of the floor is not done yet
34# Main body capping, secondary structure, floor construction The roof of the floor is not done yet
41# Main body capping, secondary structure, floor construction The roof of the floor is not done yet

There are too many unfinished parts (including large tall mounds) in the South District, and I feel extremely heavy. In addition, due to the limitations of my own perspective, I cannot list the progress one by one. The following table lists the buildings that have not been announced on 4.15 and have been capped. There are no obvious signs of construction in other sold parts (subject to online signing).

Southern District 4.15 Announcement of progress 5.16 Construction site progress Is it sold?

20#

None

Main body capping

Not sold

21#

None

Main body capping

Not sold

22#

None

Main body capping

Not sold

27#

None

Main body capping

Not sold

59#

None

Main body capping

Not sold

60#

None

Main body capping

Not sold

Dear owner friends, if you have not joined us yet and after reading this article, please take the initiative to join the organizational family. Let us safeguard our rights and interests together and handle the uncertain future together.

Machine-translated from the Chinese original 工程进度--2020.5.16 (published 2020-05-17). WeChat original ↗