On May 16, 2020, the first open day for owners of small courtyards in Dacheng after the establishment of the Interim Committee. Representatives of the Interim Committee and Tahoe staff entered the construction site to understand the progress after taking safety precautions. On rainy days, workers happened to be taking shelter from the rain, and almost no workers were seen at the construction site. Due to security concerns, access to the center field is not allowed.
Due to viewing angle issues, only the main structure can be seen, and there may be a slight deviation in reality, especially in the south area, where the view is not clear near the south. At present, except for the model houses, the decoration of the north and south finely decorated houses has not yet started.
North area perspective: 7#14th floor
South area perspective: Floor 1#9
4.15 Announcement of progress▼








The North District has all been sold out. The following table shows the progress of the main unfinished houses in the North District.
| North District | 4.15 Announcement of progress | 5.16 Construction site progress |
|---|---|---|
|
1# |
Construction of the main 7th floor completed |
The 9th floor is under construction |
|
4# |
Construction of the main 7th floor completed |
The 8th floor is under construction |
| 11# | Construction of main 3 floors completed | The 3rd floor is under construction |
| 12# | Main 2nd floor construction completed | The 2nd floor is under construction |
| 13# | Main 2nd floor construction completed | The 2nd floor is under construction |
| 14# | Construction of the first floor of the main body is completed | The 2nd floor is under construction |
| 15# | Main 2nd floor construction completed | The 3rd floor is under construction |
| 16# | Main 2nd floor construction completed | The 2nd floor is under construction |
| 17# | Construction of main 3 floors completed | The 2nd floor is under construction |
| 18# | Main roof construction | Uncapped |
| 24# | Main body capping, secondary structure construction | Missing roof tiles |
| 25# | Main body capping, secondary structure construction | Missing roof tiles |
| 26# | Main body capping, secondary structure construction | Missing roof tiles |
| 27# | Main body 3 floors completed | The 4th floor is under construction |
| 28# | Main body capping, secondary structure, floor construction | Missing roof tiles |
| 29# | Main body capping, secondary structure, floor construction | Missing roof tiles |
| 30# | Main body capping, secondary structure, floor construction | Missing roof tiles |
| 31# | Main body capping, secondary structure, floor construction | The roof of the floor is not done yet |
| 32# | Main body capping, secondary structure, floor construction | The roof of the floor is not done yet |
| 33# | Main body capping, secondary structure, floor construction | The roof of the floor is not done yet |
| 34# | Main body capping, secondary structure, floor construction | The roof of the floor is not done yet |
| 41# | Main body capping, secondary structure, floor construction | The roof of the floor is not done yet |


There are too many unfinished parts (including large tall mounds) in the South District, and I feel extremely heavy. In addition, due to the limitations of my own perspective, I cannot list the progress one by one. The following table lists the buildings that have not been announced on 4.15 and have been capped. There are no obvious signs of construction in other sold parts (subject to online signing).
| Southern District | 4.15 Announcement of progress | 5.16 Construction site progress | Is it sold? |
|---|---|---|---|
|
20# |
None |
Main body capping |
Not sold |
|
21# |
None |
Main body capping |
Not sold |
|
22# |
None |
Main body capping |
Not sold |
|
27# |
None |
Main body capping |
Not sold |
|
59# |
None |
Main body capping |
Not sold |
|
60# |
None |
Main body capping |
Not sold |
Dear owner friends, if you have not joined us yet and after reading this article, please take the initiative to join the organizational family. Let us safeguard our rights and interests together and handle the uncertain future together.